Introduction to Dell EMC Certified Specialist - Platform Engineer - Isilon Exam
The Dell EMC E20-655 Exam is challenging and thorough preparation is essential for success. This exam study guide is designed to help you prepare for the Isilon Specialist Platform Engineers certification exam. It contains a detailed list of the topics covered on the Professional exam, as well as a detailed list of preparation resources. These study guides for the Dell EMC Isilon Specialist Platform Engineers will help guide you through the study process for your certification.
E20-655 Dell EMC Isilon Specialist Platform Engineers Exam Summary
● Exam Name: Dell EMC Isilon Specialist Platform Engineers
● Exam Code: E20-655
● Exam Price: $230 (USD)
● Duration: 90 mins
● Number of Questions: 60
● Passing Score: 63%
● Books / Training:
○
PowerScale Concepts (MR-1WNISILONFUND)
○
PowerScale Hardware Concepts (MR-7WP-ISIHBG17)
○
PowerScale Hardware Installation
(MR-7WP-ISIINST17)
○
PowerScale Implementation (MR-7WP-ISIIC17)
○
PowerScale Hardware (MR-7WP-ISIHM17)
● Schedule Exam: Pearson
VUE
● Sample Questions: Dell EMC Isilon Specialist Platform Engineers Sample
Questions
● Recommended Practice: Dell EMC E20-655 Certification Practice Exam
Exam Syllabus: E20-655 Dell EMC Certified Specialist - Platform
Engineer - Isilon
1. Isilon FRU Basics and Guidelines
(11%)
-
Describe Isilon nodes and node replaceable components
-
Describe and differentiate between the internal and external networking, and
internal network cabling for Isilon nodes
-
Describe hardware safety precautions and SolVe Desktop procedures
2. Isilon Hardware Installation (27%)
-
Describe the process and activities for "planning" the installation
of Isilon hardware
-
Describe the activities and considerations for preparing the installation site
-
Describe the process for installing the Isilon nodes
-
Describe the process for installing components into the Isilon nodes
-
Describe the process for cabling an Isilon node to internal and external
networks
3. Isilon Initial Configuration (27%)
-
Describe the process and actions for creating a new cluster
-
Describe the steps for joining a node to an existing cluster
-
Describe the steps and process for completing an initial configuration
-
Describe other configuration options such as configuring ESRS, disabling
SupportIQ, and configuring SmartLock Compliance mode
4. Isilon Hardware Maintenance (35%)
- Describe the process for opening the different series
of Isilon nodes and preparing the node for service
- Describe the FRU processes, components, and associated
activities with component replacement
- Describe CRUs, their purpose, and relationship to FRUs
- Describe the FRU and CRU differences and activities
for the HD400 node series
- Describe the processes and activities to perform a
node replacement for a failed node
Dell EMC E20-655 Certification Sample Questions and
Answers
To make you familiar with Dell EMC Isilon Specialist
Platform Engineers (E20-655) certification exam structure, we have prepared
this sample question set. We suggest you to try our Sample Questions for DCS-PE E20-655 Certification to test your understanding
of Dell EMC E20-655 process with the real Dell EMC certification exam
environment.
E20-655 Dell EMC Isilon Specialist Platform Engineers Sample Questions:-
01. You
are installing a fully populated Gen 6 chassis in a customer rack and no lift
is available. Using no less than two people to lift the chassis, which
components must be removed before lifting is attempted?
a) Drive sleds and compute modules
b) Hard drives
c) Hard drives and power supplies
d) Drive sleds and power supplies
02. In
a Dell EMC Isilon, what is the minimum number of Gen 6 nodes required to create
a new cluster?
a) Two
b) Three
c) Four
d) Five
03.
What is a responsibility of a Dell EMC Isilon platform engineer?
a) Implements Active Directory integration on
the Isilon cluster
b) Creates the Configuration Guide
c) Creates the delivery schedule
d) Initializes the Isilon cluster and
handovers the initialization logs
04. You
are reinstalling the drive suitcases back into four new HD400 nodes you just
installed. What is an important consideration when putting the suitcases back
into the nodes?
a) SSD must be installed in the lowest node
number
b) SSD must be installed in the highest bay
number
c) SSD must be installed in the lowest bay
number
d) SSDs must be installed evenly across each
node
05. You
are cabling new Dell EMC Isilon Gen 6 nodes to an existing Gen 6 cluster. What
is an important consideration for the internal network connectivity?
a) Each cluster node must be connected to both
of the internal networks
b) An internal network consisting of only
Ethernet switches is not supported
c) The redundant internal network must be
configured as a single full-mesh network
d) An internal network consisting of only
InfiniBand switches is not supported
06.
Once a new Dell EMC Isilon cluster is configured, you should perform an HTTP
test. What is the proper way to test the HTTP connectivity?
a) Connect to the FQDNS name using NFS
b) Map a drive to a windows share and test if
copying a file works
c) Connect to http://FQDNS name/IFS
d) Connect to the WebUI using
https://clusteripaddress:8080
07.
During a new installation, why do SAS/SATA drives in Dell EMC Isilon Gen 5
nodes need to be fully-seated before the node powers on?
a) Node will continuously reboot
b) Drives not fully-seated will not be
recognized
c) Node will not power on
d) Drives not fully-seated will fail
08. A
company is deploying a Dell EMC Isilon cluster for the first time and requests
an Isilon platform engineer to configure the Isilon cluster.
What is
recommended to perform the initial configuration of the Isilon cluster?
a) Use the front panel to create the cluster
b) Connect using a VGA cable to access the
Configuration wizard prompt
c) Connect to the node using a serial cable
d) Access the cluster through the customer’s
network by launching a serial terminal emulator
09. Which
external Ethernet networks are available for Gen 6 nodes?
a) 1 GbE and 10 GbE
b) 1 GbE and 40 GbE
c) 10 GbE and 40 GbE
d) 10 GbE and 100 GbE
10. To
maintain high-availability on Dell EMC Isilon Gen 5 or Gen 6 clusters, two
back-end switches are required. What is the proper installation of the back-end
switches?
a) Switch A should be connected to the left
PDU and switch B should be connected to the right PDU
b) Switch ports should face the rear of the
rack
c) Switch power supplies require a UPS for
each connected circuit
d) When racking the switches, leave at least
1U of space between the switches to allow adequate air flow for cooling
Answers:-
Answer
1:- a
Answer
2:- c
Answer
3:- d
Answer
4:- c
Answer
5:- a
Answer
6:- d
Answer
7:- b
Answer
8:- c
Answer
9:- c